PMP考试练习题及参考答案(23)
| 
											1 Work packages are used to:    A Represent units of work at a level where work is performed.   B Clearly distinguish one work package from all others assigned to a single functional group.   C Limit the work to be performed to relatively short periods of time.   D All of the above.   E A and B only   ans:D   2 Project life cycles are very useful for _____ and _____ .   A Configuration management, termination   B Objective setting, information gathering   C Standardization, control   D Configuration management, weekly status updates   E Approval, termination   ans:C   3 Which of the following are included as part of a scope statement?   A Project justification   B Project deliverables   C Project objectives   D All of the above   E B and C   ans:D   4 The initial document that formally recognizes the existence of a project is the _____ .   A Scope baseline   B Management plan   C Project charter   D Configuration control report   E None of the above   ans:C   5 Which of the following is not a scope management process?   A Initiation   B Scope planning   C Scope Definition   D Scope change control   E Scope verification   ans:D   6 In which of the following scope management processes is the scope management plan prepared?   A Initiation   B Scope planning   C Scope Definition   D Scope change control   E Scope verification   ans:B   7 The project charter is prepared in which scope management process?   A Initiation   B Scope planning   C Scope Definition   D Scope change control   E Scope verification   ans:A   8 The work breakdown structure (WBS) is first developed in which scope management process?   A Initiation   B Scope planning   C Scope change control   D Scope Definition   E Scope verification   ans:D   9 In which of the following scope management processes are subject matter experts used?   A Initiation   B Scope planning   C Scope Definition   D Scope change control   E Scope verification   ans:A   10 A Work Berakdown Structure is most useful for:   A Identifying individual tasks for a project.   B Scheduling the start of tasks.   C Developing a cost estimate.   D Determining potential delays.   E A and C.   ans:E   11 The scope statement provides   A A basis for future decisions about a project.   B A baseline to accomplish verification measures.   C A baseline to evaluate potential scope changes.   D All of the above   E B and C only   ans:D   12 A work breakdown structure:   A assures all work is identified.   B subdivides the project into manageable segments.   C provides the project sponsor with a time-phase task summary.   D both A and B.   E All of the above.   ans:D   13 Budgetary estimates are the output of the _____ phase(s) of the project.   A conceptual   B development   C implementation   D finish   E All of the above.   ans:B   14 Which of the following are included in the Acquisition phase(s) of the project life cycle.   A concept and development   B development and planning   C execution and phase-out   D planning and implementation   E concept and planning   ans:C   15 Project alternatives are examined during the _____ phase of the project   A conceptual   B finish   C development   D implementation   E A and C   ans:E   16 We assign human and non-human resources in the _____ phase of the budget.   A conceptual   B planning   C development   D implementation   E close-out   ans:D   17 Project trade-offs vary between   A risk, cost and schedule.   B direct cost, indirect cost, and resource availability   C quality, schedule and time   D cost, quality and schedule   E contract terms, scope and budget   ans:D   18 The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.   A budget, schedule   B quality requirements, schedule   C size, type of industry   D nature, size   E project manager, sponsor   ans:D   19 The time necessary to complete a project is called the _______ of a project.   A Implementation Time   B Life Cycle   C Operation Time   D Critical Path   E Completion Phase   ans:B   20 When a project incorporates an Organizational Breakdown Structure (OBS), it is integrated with the WBS at the   A task   B level of effort   C sub-task   D project   E work package   ans:E | 