PMP考试每天一练-2023年PMP考试模拟题72

作/转载者:PMP团购网      发布时间:2023/6/9        点击: 523

PMP考试练习题一:

在与相关方召开的批准会上,另一名之前没有提供意见的相关方,质疑项目基准的有效性。在冗长的讨论之后,很明显无法获得最后批准。项目经理应该采取的适当措施是什么?

During the approval meeting with the stakeholders, another stakeholder, who has not previously provided input, challenges the project baseline. After lengthy discussions, it becomes clear that final approval cannot be given.What is the appropriate action for the project manager to take?

A:说明项目基准的详细情况,并从计划过程开始评估意见数据

Clarity the details of the baseline and evaluate the input date from the planning process

B:向相关方解释在该阶段无法考虑这个意见的原因

Explain to the stakeholder why this input cannot be considered at this stage of the project

C:让相关方提出变更请求评估新的情况

Ask the stakeholder to formulate a change request to evaluate the new situation

D:坚持获得项目计划批准,并在后续阶段对新意见开展调整

Insist on project plan approval and investigation of the new input at a stage

PMP考试答案解析:题环境描述,现在正在开批准会议,也就是说基准只是一个概念,目前还未获得批准,开会的目的就是为了批准,没有经过批准的基准不能算为真正的基准,准确的称谓应该是:待批准的基准,因此,既然还没有批准就不存在变更问题,变什么呢?没有批准不用申请变更,所以选 D 错误!相关方不同意基准,说明之前没有征得该相关方的意见,忽略了该相关方,他对这个基准形成的过程和数据不清楚,因此要从头开始介绍给他,与他一起分析相关数据,让他参与进来才是正确选项,所以选 A。

PMP考试参考答案:A

PMP考试练习题二:

当一个过程处于受控状态中,对此过程可以怎么做?

A. 不应该调整该过程

B. 应该调整该过程,以便提高产品质量

C. 应该在项目阶段结束时,及时调整该过程

D. 应该为了使工作更具挑战性,而调整该过程

PMP考试参考答案:A