PMP考试每天一练-2023年PMP考试模拟题69
PMP考试练习题一: 项目经理被要求为两个潜在项目执行成本效益分析。项目 A 成本为$12 亿美元,潜在效益为$60 亿美元,未来运营成本为$15 亿美元;项目 B 成本为$14 亿美元,潜在效益为$70 亿美元,未来运营成本为$1 亿美元。项目经理应该推荐哪一个项目? A project manager is asked to perform a cost-benefit analysis for two potential Project A costs US$ 1.2billion. With potential benefits of US$ 6 billion and future US$ 1.5 billion.Project B costs US$ 1.4 billion, with potential benefits of US$ 7 billion and future US$ 1 billion.Which project should the project manager recommend? A:项目 B;因为潜在效益减去执行成本所得的值大于项目 A 所得值。 Project B; the potential benefits minus the costs to implement are greater calculation for project B:项目 A;因为执行成本低于项目 B。 Project A; the cost to implement is less than project C:项目 B;因为潜在效益减去执行成本和未来运营成本所得的值大于项目 A。 Project B; the potential benefits minus the implementation and future greater than the same calculation for project A. D:项目 A;因为潜在效益加上未来运营成本所得的值小于项目 B 所得值。 Project A; the potential benefits plus the future operating costs are less than calculation for project B PMP考试答案解析:商业论证从商 业视角描述必要的信息,并且据此决定项目的期望结果是否值得所需投资。高于项目级别的经 理和高管们通常使用该文件作为决策的依据。一般情况下,商业论证会包含商业需求和成本 效益分析。收益=潜在效益-投资成本-运营成本 PMP考试参考答案:C PMP考试练习题二: 过程分析旨在: A.发现非增值活动 B. 提高项目产品质量 C. 降低生产成本 D. 满足相关方满意度 PMP考试参考答案:A |